The right to participate in the public tender is granted to all Balancing Service Providers that have a valid mFRR Balancing Service Agreement with the Transmission System Operator and have provided the appropriate financial security (deposit or bank guarantee).
For the purposes of the Rules for the Procurement of aFRR and mFRR Balancing Capacity and/or Balancing Energy, September 2026 (HOPS 9/2026), Balancing Service Providers are defined as Bidders.
Bidders submit bids for:
- provision of mFRR balancing capacity,
- balancing energy from contracted mFRR balancing capacity,
- balancing energy from voluntary bids.
A Bidder whose mFRR balancing capacity bid has been selected for the relevant balancing service provision period is entitled to transfer all or part of its obligation to another Balancing Service Provider.
Procurement process overview:
|
Product mFRR R2 |
|
|
Min bal.
capacity bid size |
1 MW |
|
Activation method |
Manually DA (direct) and SA (schedule) |
|
Bid
divisibility (bal. capacity) |
Divisible, in 1 MW
increments |
|
FAT |
≤ 15 min |
|
Direction |
mFRR+ R2: (+) increase in delivery
to the grid or decrease in withdrawal from the grid; |
|
mFRR−
R2: (−) decrease in delivery to the grid or
increase in withdrawal from the grid |
|
|
Maximum indivisible mFRR balancing capacity bid |
20 MW |
|
Maximum balancing
energy bid |
20 MW |
|
Maximum indivisible balancing energy bid |
20 MW |
|
Minimum activation
duration |
30 min** |
|
Maximum activation duration |
2 h**,*** |
|
Time between
activations |
mFRR+ R2: 8 h **,*** |
|
mFRR- R2: 4 h
**,*** |
|
|
Energy Bid
granularity |
Portfolio, regulation group or regulation
unit* |
** The balancing product parameters (minimum activation duration, maximum activation duration and time between two activations) apply to balancing energy bids covering two or more consecutive MTUs that relate to the same balancing product and the same resource object providing the service (regulation unit or group) and have the same bid quantity [MW].
*** With the consent of the Balancing Service Provider, a longer maximum activation duration and/or shorter time between two activations than specified above may be used, as set out in Annex 1 to the Agreement.
|
Products |
Direction |
Price
Limit (EUR/MW/h)
|
|
mFRR+R2 |
+ |
6,64 |
|
mFRR−R2 |
− |
9,50 |
|
Product |
Direction |
Price Limit (EUR/MWh) |
|
mFRR+R2 |
+ |
not prescribed* |
|
mFRR−R2 |
- |
not prescribed* |
The mFRR balancing capacity tender covers six four-hour time blocks:
- 00:00–04:00 (hours 1–4 of day D)
- 04:00–08:00 (hours 5–8 of day D)
- 08:00–12:00 (hours 9–12 of day D)
- 12:00–16:00 (hours 13–16 of day D)
- 16:00–20:00 (hours 17–20 of day D)
- 20:00–24:00 (hours 21–24 of day D)
Bid submission period:
- GOT: 00:00 seven (7) days before the delivery day (00:00, D-7)
- GCT: 10:00 on the day preceding the delivery day (10:00, D-1)
- POT: 10:30 on the day preceding the delivery day (10:30, D-1)
mFRR balancing capacity bids are selected using a minimum-cost optimization method (MILP algorithm), as defined in Annex 5 of the Rules for the Procurement of aFRR and mFRR Balancing Capacity and/or Balancing Energy, September 2026 (HOPS 9/2026).
- Balancing energy bid resolution: 1 MTU (15 minutes)
- GOT: 7 days before the individual MTU (MTU – 7 days)
- GCT0: 14:30 on the day preceding the delivery day (14:30, D-1)
- GCT: 25 minutes before the start of the relevant MTU (MTU – 25 min).
Balancing capacity and balancing energy bids shall be submitted electronically via the HOPS IT system – Balancing Platform.